You Closed the Construction Loan. Can Your Books Clear the First Draw?


By Douglas Kohn, MBA, CPA
South Florida construction capital is still closing. On November 6, Florida YIMBY reported that Hernandez Development & Construction and PTM Partners secured a $17.325 million construction loan from Pinnacle Financial Partners for Palm Beach Commerce Center, a 93,556-square-foot Class A industrial project at 8530 Belvedere Road in unincorporated Palm Beach County. The financing closed October 26, 2026, as site work got underway, with delivery targeted for the third quarter of 2027.
A few days earlier, JVP Management announced a $140.2 million senior construction loan to Alta Developers for Alta New River, a planned 35-story, 400-unit luxury rental tower at 100 SW 6th Street in Fort Lauderdale. Construction is expected to begin in November 2026, with completion anticipated in the fourth quarter of 2028. And Cohen Brothers Realty said construction financing is in place for West Palm Point, the downtown West Palm Beach office tower the developer describes as a $400 million project targeting delivery in the first quarter of 2029.
Closing those loans is the headline. Clearing the first draw is the operating problem. Lenders do not wire the full commitment at closing. They fund against verified progress, inspections, lien waivers and a budget that still covers cost to complete. If your job-cost ledger, pay applications and lender schedule of values do not talk to each other, the draw sits.
Here's what a lender-ready construction draw package needs—and how the books have to support it.
What does the lender actually test on a progress draw?
The FDIC's Risk Management Manual of Examination Policies, Section 3-2 Loans, describes progress payment plans used on larger commercial projects as generally based on monthly disbursements totaling 90 percent of the value, with 10 percent held back until the project is completed. Examiners also expect banks to compare draws to degree of completion, compare budget projections to actual costs, and advance funds only after written inspection reports, lien searches and title updates, per the FDIC's Construction and Land Development examination module. Your package has to survive that same logic even when your lender is a debt fund or private credit shop rather than a bank.
What belongs in the draw package before the inspector shows up?
A signed pay application (often AIA G702/G703 or the lender's equivalent) that ties percent complete by line item to the approved schedule of values. An updated budget-to-actual by cost code, with committed costs shown separately from incurred costs. A change-order log that separates approved changes from pending ones. Conditional lien waivers for the current draw and unconditional waivers for the prior draw from the GC and major subcontractors. Soft-cost invoices and proof of payment for owner-direct items. And a one-page bridge from the job-cost / WIP ledger to the dollars requested on this draw.
How do you keep a three-way tie between WIP, the draw and the loan balance?
Every month, three numbers have to agree: cumulative costs posted to WIP (or construction in progress) by cost code, cumulative draws funded by the lender, and the construction loan balance on the lender statement. Gaps usually mean something was posted to the wrong code, a soft cost never made it into the borrowing base, retainage was booked one way on the pay app and another way on the GL, or a change order hit the field before it hit the approved budget. Rebuild the bridge every month, not the week the draw is late.
Here's an example with made-up numbers. A Palm Beach County industrial project has a $17.3 million construction commitment and an approved hard-and-soft budget of $19.0 million (equity covers the rest). Through month three, job cost shows $2,400,000 incurred. Retainage withheld on GC pay apps is $180,000, so earned-and-billed hard costs are $2,220,000 net of retainage. Soft costs eligible under the loan agreement (architect, permits, interest during construction that qualifies for capitalization) add $310,000. Prior draws funded total $2,100,000. This month's eligible request, after retainage and prior advances, is about $430,000—if every line ties to an approved schedule-of-values column and the inspector confirms the work. If $200,000 of "miscellaneous construction" sits in a catch-all GL account with no matching SOV line, that piece does not fund until it is reclassified.
Where do retainage and change orders break the draw?
Retainage is not a rounding plug. It is a contractual holdback that also shows up as retainage payable to subs and, for the GC, retainage receivable from the owner or lender structure. If the pay app withholds 10% but the GL still shows the full amount as cash due, your aging and your cash forecast are both wrong. Change orders break draws when field work starts before written approval. Pending changes can appear in a cost-to-complete column for visibility, but they should not enter the borrowing base until they are approved and the schedule of values is updated. That is an accounting control, not just a project-management preference.
How should construction-period interest show up in the package?
Interest on a construction loan during the active build is often capitalized into the project asset under FASB ASC 835-20 when expenditures have been made, activities necessary to get the asset ready for its intended use are in progress, and interest is being incurred. Capitalization generally stops when the asset is substantially ready for its intended use. Put the capitalized-interest schedule in the soft-cost section of the draw package so the lender can see the rate, the average accumulated expenditures and the amount capitalized this period—not a single journal entry labeled "interest" with no support. (For the deeper treatment of when interest stops being an expense, see Ultramar's earlier note on construction-loan interest capitalization.)
When does a real estate or construction company need a fractional CFO for draw packages?
When the loan is closed and the monthly requisition still takes a week of email archaeology. A fractional CFO or outsourced CFO rebuilds the WIP-to-draw bridge, documents retainage, separates approved vs pending change orders, capitalizes interest correctly and packages the file the way an inspector and credit officer expect to see it. A fractional controller keeps the monthly job-cost close clean so the next draw does not reopen last month's mess.
That's the fractional CFO work we do at Ultramar for real estate and construction owners in Boca Raton, South Florida and New York, and at SoFla Prime Consulting for South Florida small businesses and nonprofits that need a fractional CFO, fractional controller or outsourced accounting team without a full-time hire.
FAQ
Did South Florida still close construction loans in late October and early November 2026?
Yes. Palm Beach Commerce Center closed a $17.325 million Pinnacle construction loan (announced November 6; closed October 26). JVP announced a $140.2 million senior construction loan for Alta New River on November 2. Cohen Brothers said construction financing is in place for West Palm Point, described as a $400 million office project.
How much do progress-payment construction loans typically retain?
The FDIC's Section 3-2 Loans manual describes progress payment plans on larger commercial projects as generally based on monthly disbursements totaling 90 percent of the value, with 10 percent held back until completion. Individual loan documents control the exact retainage percentage.
What is a three-way WIP–draw–loan tie-out?
A monthly reconciliation that proves cumulative job costs (WIP), cumulative lender draws and the construction loan balance on the lender statement all tell the same story, with documented reconciling items for retainage, soft costs and timing.
Can pending change orders be included in a draw?
Usually not in the funded borrowing base until they are approved and the schedule of values is updated. Show them in cost-to-complete for visibility so the lender can see remaining risk.
Can a CPA or fractional CFO prepare the draw package if the GC runs the pay apps?
Yes. The GC prepares pay applications for work in place. A fractional CFO or controller rebuilds the budget-to-actual, retainage, soft-cost and capitalized-interest schedules and ties the request to the loan agreement so the sponsor is not guessing when the inspector asks a question.
If you own or operate real estate or construction companies in Boca Raton, South Florida or New York and just closed—or are about to close—a construction loan, contact me at Ultramar to rebuild a lender-ready draw and WIP package before the first requisition.
Douglas Kohn, CPA, MBA, is a fractional CFO for real estate, construction and small businesses in South Florida and New York.
This post is general information, not lending, legal or tax advice for your project or loan.
Sources
Florida YIMBY, "Hernandez Development & Construction And PTM Partners Secure $17.3 Million Construction Loan For Palm Beach Commerce Center," November 6, 2026: https://floridayimby.com/2026/11/hernandez-development-construction-and-ptm-partners-secure-17-3-million-construction-loan-for-palm-beach-commerce-center.html
JVP Management via PR Newswire, "JVP Management Provides $140.2 Million Construction Loan for Alta New River in Downtown Ft. Lauderdale," November 2, 2026: https://www.prnewswire.com/news-releases/jvp-management-provides-140-2-million-construction-loan-for-alta-new-river-in-downtown-ft-lauderdale-302925316.html
22Miami, "West Palm Point developer says construction financing is in place," November 4, 2026: https://www.22miami.com/article/west-palm-point-financing-2026-10-29
FDIC, Risk Management Manual of Examination Policies, Section 3-2 Loans: https://www.fdic.gov/resources/supervision-and-examinations/examination-policies-manual/section3-2.pdf
FDIC, Construction and Land Development examination module: https://www.fdic.gov/risk-management-manual-examination-policies/construction-and-land-development-lending.pdf
FASB Accounting Standards Codification Topic 835-20, Capitalization of Interest (qualifying assets; capitalization period and measurement).